Arian Silver Reports Excellent Progress on Processing Plant Reassembly at San José Project

Arian Silver Corporation (the "Company" or "Arian Silver") a silver exploration, development and production company with a focus on projects in the silver belt of Zacatecas, Mexico, reports that it continues to make excellent progress on the refurbishment and reassembly of the processing plant (the "Plant") at the Company's San José project site.

Highlights:

  • Refurbishment and transportation of the Plant to the new site at San José completed and under budget;
  • Installation of a new transmission line to supply grid power to the new plant site completed;
  • Pre-construction earthmoving at the new site completed;
  • Mounting and installation of the plant on site at San Jose nearing completion;
  • New decline ramp into the Soledad section of the San José mine intersected with the vein;
  • Financing discussions continue to advance;
  • Images showing the progress at San Jose are available on the Company's website www.ariansilver.com/s/Sanjose.asp

Jim Williams, Chief Executive Officer of Arian Silver, commented: "I am delighted to report continued rapid progress with the refurbishment programme of our processing plant, which has a stated capacity of up to 1,500 tonnes per day once fully commissioned. This Plant, together with its extensive inventory of spare parts is now on site pending the completion of its reassembly and commissioning, which is also on-track for the end of the year in readiness for commercial production.

Arian Silver's financing negotiations continue to progress and the Board looks forward to updating shareholders as soon as possible."

Processing Plant

In August 2013, Arian Silver purchased a custom processing plant, located 60km from the Company's mine site at San José. The acquisition, refurbishment and reassembly of the Plant is expected to enable Arian Silver to increase production in a modular manner up to a maximum capacity of 1,500 tonnes per day. This, together with increased mine production and the elimination of Arian Silver's reliance upon third-party toll millers, will provide significantly increased operational control, which should translate into significantly reduced operational costs.

The refurbishment of the Plant was completed significantly under budget and remains on schedule to begin commissioning by the end of 2014.

Ground works at the plant site are substantially complete, the reinforced concrete foundations are mainly completed, and the associated plant equipment is currently being installed. The construction and refurbishment of the site offices and other associated buildings has also been completed and the buildings are ready for use.

The installation of a 35KV multi-phase power line and associated spurs has been completed for Arian Silver's exclusive use at the Plant, which is rated to accommodate any planned upgrades at the Plant. This is in addition to the existing 13KV exclusive power line to the San José mine.

Photographs illustrating the progress of the development of the Plant are available on the Company's website, at www.ariansilver.com/s/Sanjose.asp.

San José mine

Mine development continues in the San José and Santa Ana sections of the mine. Construction has commenced on an additional 4x5m decline ramp at the Soledad section of the mine, which is approximately 1km west of the main San José decline ramp. This work is part of the mine development program designed to ensure the mine can sustainably produce at up to 1,500 tonnes per day.

The mine has been dewatered to the 180m level (180m below the surface), enabling access to new areas, and further significant development has occurred at these deeper levels.

Financing

The Company's negotiations over a comprehensive financing solution for the San José Project continue to advance positively. The new financing solution is intended to retire the existing convertible note facility and complete the San José project development. As reported on 29 August 2014, the convertible note facility has been extended to 30 September 2014. The Board remains confident of a positive outcome and shareholders will be updated as soon as possible.

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.