North American Palladium Ltd. ("NAP") (the "Company") announced today that milling operations at its Lac des Iles ("LDI") mine site were successfully restarted on June 26, 2015. Underground operations continued during the suspension of milling operations resulting in a large stockpile of approximately 250,000 tonnes of crushed ore on surface which is available for processing.
Initial mill startup has been at approximately 8,400 tonnes per day ("tpd") which will be increased to approximately 13,000 tpd for a period in July to work through the stockpile before reverting back to 8,400 tpd as per the 2015 plan.
Prior to the restart of milling operations, the Company received a dam safety report from an independent third-party engineering consulting firm that reconfirmed the integrity of the containment structures at LDI's tailings management facility. The Company also successfully restored water balance levels at LDI to within permitted operating levels. Following consultations with relevant provincial ministries, the Company was in compliance with all criteria required for the restart of milling operations.
"Significant efforts by team members across the Company, led by those on-site at LDI, have put us in a position to restart milling operations," said Phil du Toit, President and CEO. "I would also like to acknowledge the cooperation and support of various government ministries and other stakeholders who have been working with LDI."
Since June 18, 2015, only treated water has been discharged. Extensive downstream monitoring and testing to date in the LDI reclaim ponds and of the treated and untreated water released in downstream discharge areas has confirmed the water to be non-toxic and there have been no observed detrimental effects on aquatic life.
Frequent consultation has been maintained with various First Nations groups in the area with regard to the recent water discharge and the actions being taken by LDI. The potential impact of the discharge on the environment, if any, has yet to be determined and LDI is working with experts in the field to prepare and implement a long term monitoring and remediation plan in consultation with stakeholders.
Technical Information and Qualified Persons
Mr. James Gallagher, the Company's Chief Operating Officer and a Qualified Person under National Instrument 43-101, has reviewed and approved all technical items disclosed in this news release.
About North American Palladium
NAP is an established precious metals producer that has been operating its Lac des Iles mine located in Ontario, Canada since 1993. LDI is one of only two primary producers of palladium in the world, offering investors exposure to palladium. The Company's shares trade on the TSX under the symbol PDL and on the OTC Pink under the symbol PALDF.