Purepoint Uranium Group Inc. today reported the results of the next series of four holes drilled at the Spitfire Zone. Drilling now confirms that uranium mineralization is continuous for at least 200 metres down-dip of a graphitic shear zone beginning just below the unconformity.
High-grade uranium mineralization is consistently seen in association with brittle structures crosscutting the shear zone. Purepoint is the operator of the Hook Lake project on behalf of its Joint Venture partners Cameco Corp. and AREVA Resources Canada Inc.
"We are particularly encouraged by the thickness of mineralization where it is associated with cross-cutting structures," said Scott Frostad, Purepoint's V.P. Exploration. "HK-16-47 is mineralized for over 30 metres within a 40 metre interval while HK-16-52 came back with over 18 metres of mineralization and both these intercepts are considered close to true width."
"The continued expansion of Spitfire is helping us define the potential for yet another regional deposit." said Chris Frostad, President & CEO at Purepoint. "We are very excited at the prospect of what the remainder of this season may deliver."
Highlights:
- Uranium mineralization is primarily associated with the upper contact of a graphitic/pyritic shear zone and a halo of moderate to intense clay alteration.
- High grade mineralization is associated with brecciation that occurs sub-parallel to but cross-cuts the graphitic shear zone.
- Highlights of the downhole gamma probe results are HK16-47 with 19.6 metres of 0.82% eU3O8 that includes 7.2 metres of 1.3% eU3O8 and HK16-52 with 18.5 metres of 0.68% eU3O8 that includes 4.3 metres of 2.6% eU3O8.
- The targeted graphitic shear zone remains open both along strike and to depth.
- Drilling is ongoing and is currently targeting the projected intersection of known brittle structures and the graphitic shear zone.
Spitfire Holes to March 14, 2016
Drill hole HK16-47 was collared as a 35 metre NNW step-out from HK16-43 with an azimuth of 295 degrees and a dip of -80 degrees. The unconformity was reached at 153 metres then strongly clay altered granitoid rocks intercalated with metasedimentary rocks were encountered to 193 metres. Numerous clay altered fractures both crosscutting and parallel to foliation returned 0.06% eU3O8 over 5.8 metres. Strongly-sheared chloritized pelitic gneiss was drilled to 201 metres followed by strongly sheared graphitic pelitic gneiss to 208 metres and returned 10.9 metres of 0.15% eU3O8. Granitoid rocks with strong clay alteration occur to 218 metres followed by 19.6 metres of brick-red, oxidized rocks hosting uranium mineralization that is centered on a weakly radioactive 1.2-metre-wide chloritized brittle fault and increases in concentration into the adjacent wall rock. The downhole probe returned 19.6 metres of 0.82% eU3O8 that included 7.2 metres of 1.3% eU3O8. Strongly clay-altered granitoid gneisses and metasediments were encountered to the end of hole at 380 metres.
Drill hole HK16-49 was collared as a 25 metre NNE step-out from HK16-43 with an azimuth of 285 degrees and a dip of -80 degrees. The unconformity was intersected at 151 metres then strongly clay altered granitoid and pelitic rocks were drilled to 224 metres. A fault zone at 220 metres was associated with 6.0 metres of 0.12% eU3O8. The graphitic shear was encountered from 224 to 244 metres and returned 8.0 metres of 0.30% eU3O8 and a second interval with 3.5 metres of 0.55% eU3O8 that includes 0.8 metres of 1.6% eU3O8. Clay and chlorite altered granodioritic gneiss continues to 272 metres and is then unaltered to the completion depth of 398 metres.
Drill hole HK16-51 was collared 90 metres NW of HK15-27 (2.8 metres of 2.23% U3O8) with an azimuth of 315 degrees and a steeper dip of -85 degrees. The unconformity was intersected at 155 metres then strongly silicified granitoid and pelitic rocks were drilled to 262 metres becoming clay altered to 333 metres. The graphitic shear was encountered from 333 to 346 metres and returned 6.2 metres of 0.10% near the upper contact. Graphitic/pyritic pelite mixed with 30 to 50% quartz vein material continued to 377 metres followed by clay altered granodioritic gneiss to the completion depth of 429 metres.
Drill hole HK16-52 was collared 15 metres W of HK16-43 and drilled with an azimuth of 315 degrees and a steep dip of -85 degrees. The unconformity was intersected at 158 metres then strongly clay and chlorite altered granitoid and pelitic rocks were drilled to 244 metres. The graphitic/pyritic shear was encountered from 244 to 284 metres and returned 18.5 metres of 0.68% eU3O8 that included 4.3 metres of 2.6% eU3O8. Granodioritic gneiss with clay alteration was then encountered to 487 metres then the unit is unaltered to the completion depth of 497 metres.