Kombat Copper Reports Positive Progress of Pre-Production Activities at Kombat Mine

Kombat Copper Inc. ("Kombat Copper" or the "Company") is reporting on the positive progress of pre-production activities at the Kombat Mine. Kombat Copper's local mining contractor, EBM Mining Namibia (Pty) Ltd. ("EBM"), has been active at the mine site and have identified which activities and tasks are necessary to recommence mining at the Kombat Mine and have provided the Company with an update on their findings and progress.

EBM is responsible for the costs associated with planning and refurbishment, hiring of staff and workers and the procurement of supplies and equipment.

Health and Safety

EBM has been reviewing the health and safety aspects of the project and are implementing a full health and safety plan during the pre-production phase of restarting the mine.

Plant Refurbishment Update

The plant clean-up has been progressing well and EBM has reported that they are pleased with the progress they are seeing. The commissioning date of the plant is expected to be in Q3 2016 and EBM is confident that they will meet this date. Repairs are currently being performed on pipe fittings and electrical equipment with the goal of getting the full site clean and ready for operation by the target date. Supervision and labour are currently on site working on the refurbishment.

Concentrator Refurbishment Update

Crushing Plant - Cleaning of the crushing plant is in progress with the focus on refurbishment. Repairs are being made to feed chutes and conveyors that require replacement and the Symons Crusher is being stripped, cleaned and rebuilt.

Grinding Plant - Cleaning of the grinding plant was completed in late January 2016 and included the following results:

  • Pumps were opened, cleaned and refurbished
  • Inspection was completed on all rod and ball mills with some repairs required specifically on the rod mill gear and pinion along with the replacement of some of the shell liners and lifters. The mill drives have been cleaned, inspected and lubricated. All required part and spares have been ordered.

Floatation Plant - Work at the flotation plant is scheduled for completion at the end of March 2016 and includes the cleaning and refurbishment of the flotation cells. Currently, EBM is negotiating with a local company to procure needed parts to complete the work on the flotation circuit.

Geology

EBM has been working through the geological reports and extensive data provided by Kombat Copper and good progress has been made in relation to mine planning and scheduling.

Equipment

All necessary equipment and parts not on site have been, or are in the process of being acquired or sourced through contractors.

Paul Bozoki, President and CEO of Kombat Copper, commented: "We are very pleased with the rapid progress we are seeing at the Kombat Mine and the quality of work being performed by EBM. Because of this, I am confident that we will meet our goal of getting the Kombat Mine into production in late 2016 and begin generating cash flow for the Company."

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.