Sep 26 2016
Austral Gold Limited ('Austral' or 'the Company') is pleased to provide an update of current activities at its 100% owned Guanaco Mine and Amancaya project in Chile. Construction of a new agitated leach and Merrill-Crowe circuit at Guanaco is well advanced and is expected to be completed prior to the end of the year. The Company is planning to undertake a Pre-Feasibility Study and Technical Report for the combined Amancaya and Guanaco project. Infill drilling for this study commenced in September at Amancaya.
Stabro Kasaneva, Austral CEO, stated "I am very happy to report on our efforts to advance the potential combination of Guanaco operations with our high grade Amancaya project. We are moving forward on a number of fronts to commence a Pre-Feasibility Study that we expect will justify our faith in the Amancaya project and its potential to substantially extend the life of mine of Guanaco."
Guanaco Agitated Leach Plant Progress Report
The Company budgeted US$16.5 million to the construction of this plant, which has been funded by local banks and free cash flow from Guanaco operations. The decision to build this plant was based on internal studies focused on treating Amancaya production at the Guanaco plant. Construction began in May of 2016 but no economic analysis has been completed to date and the Company expects to complete and test the plant by the end of the year. Internal bottle roll studies have indicated that recoveries of gold could be improved relative to recovery from the current heap leach, but the decision to construct the new plant was not based on a feasibility study. As a result, economic and technical viability of the new plant remains subject to uncertainty and there can be no assurance that the Company can achieve any particular level of recovery of minerals or improve the cost of such recovery.
Prefeasibility Study
Austral is planning to undertake a Pre-Feasibility Study and Technical Report (the "Amancaya and Guanaco Technical Report") on operating the Guanaco operation and Amancaya project as one operation. The Company is pushing ahead with development activities at the Amancaya project to allow for completion of a Pre-Feasibility Study during calendar year 2017. Infill drilling commenced in early September with an initial plan for 94 drill holes (13,321 m), which are expected to be completed before the end of the year.
The drilling is aimed primarily at upgrading the resource of 64,200 t @ 10.19 g/t Au and 32.72 g/t Ag indicated category and 1.665 million tonnes inferred category @ 7.2 g/t Au and 53.1 g/t Ag reported in the Company's National Instrument 43-101 compliant technical report titled Guanaco Gold Project, Antofagasta Province, Region II, Chile, NI 43-101 Technical Report, which had an effective date of November 24, 2015 and which was amended June 30 2016, and filed on July 25, 2016 on the Company's profile on www.sedar.com).
The Company intends to truck production from initial open pits then from underground operations at Amancaya to the new Guanaco plant. The Company plans to incorporate treatment of production from the Guanaco operation and possible retreatment of some of the heap leach pads into the planned Pre-Feasibility Study.
Qualified Person's Statement
Dr Robert Trzebski is a Director of Austral Gold Limited. He has a degree in Geology, PhD in Geophysics, Masters in Project Management and has over 20 years professional experience in mineral exploration, project management and mining services.
Dr Trzebski is a fellow of the Australian Institute of Mining and Metallurgy (AUSIMM) and qualifies as a Qualified Person as defined in the 2004 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves.' Dr Trzebski consents to the inclusion of the resources contained in this announcement.