Mar 9 2017
Highlights:
- Akwasiso drilling campaign underway to upgrade 3.85 million tonnes of Inferred Resources containing 193,000 ounces of gold to an Indicated classification
- Significant intersections received for Akwasiso drilling, including:
- 7 metres at 13.05 g/t gold
- 11 metres at 3.21 g/t gold
- 54 metres at 1.70 g/t gold
- 33 metres at 1.50 g/t gold
- Akwasiso deposit is situated on a current mining lease and supplementary permitting is expected to be complete in H2 2017
- Project 5 Million under construction and expected to be completed a quarter ahead of schedule
- Expansion capital costs are fully funded from current internal resources and cash generated from operations
Asanko Gold Inc. is pleased to announce positive initial results from the Akwasiso drilling campaign, which is currently underway targeting an upgrade of 3.85 million tonnes ("Mt") of Inferred Resources containing 193,000 ounces of gold to an Indicated classification.
Akwasiso is a large scale satellite deposit located 5 kilometers north east of the processing facility, which is in the process of being upgraded to increase throughputs from 3.6 million tonnes per annum (Mtpa) to 5Mtpa. The plant upgrade, "Project 5 Million", is tracking well ahead of schedule and expected to be completed and ready for commissioning at the beginning of Q4 2017. The project's capital costs, including the opening up of Esaase and the installation of the overland conveyor belt over the next two years, is fully funded from existing cash resources and cash generated from operations over this period. Project 5 Million is expected to further increase gold production in 2018 as well as lower All-in sustaining costs ("AISC").
Mining of the Akwasiso deposit is expected to commence during 2018 to augment mill feed from both the Nkran and Dynamite Hill pits, providing mining flexibility in anticipation of the commissioning of the Esaase pit and overland conveyor in H2 2018. The Akwasiso incremental, at surface oxide ounces are expected to have a lower cost profile than the current Nkran operations, thereby contributing to lowering AISC in 2018. The Akwasiso deposit is on an existing mining permit and only requires a supplementary permit application, which is well advanced. Asanko anticipates receiving full permits for Akwasiso in H2 2017.
Peter Breese, President and CEO, commented, "The results received so far from the Akwasiso infill drilling program support a significant upgrade of Inferred resources to the Indicated classification. These near-surface, incremental oxide ores are cheap to mine and process and will form part of the 2018 mine plan, along with Nkran and Dynamite Hill, to supply 5Mtpa of ore to the processing plant once the plant upgrades have been completed. The plant upgrades, which will be funded from internal cash resources, are currently tracking well ahead of schedule and we expect hot commissioning to commence early in Q4 2017.
Since we received the more conservative resource model for Nkran, which we published in February 2017, Asanko has now embarked on a pit optimization process to establish the optimal NPV for all eleven pits making up the Asanko Gold Mine Mineral Reserve base. This optimization will be included in the new feasibility study that is due for publication in Q2 2017."
The infill drilling campaign is close to completion, with 4,437 meters of the planned total of 4,800 meters drilled. Intersections are shown in Table 1 (refer to the Appendices at the end of this release), and highlights include a number of 30-50m mineralized zones evident in boreholes 016 and 018, as well as high grade intercepts. Upon receipt of all assays, the Akwasiso Mineral Resource Estimate ("MRE") will be revised and an updated pit design will be completed. Two cross sections showing key intercepts are also included in the Appendices.
Akwasiso is a satellite deposit which was acquired in Q3 2016 and is situated within the Nkran Shear corridor five kilometers north east of the Nkran Pit. The deposit shows similar geological characteristics to Nkran, with at least three mineralized structures within a sandstone-siltstone sequence and an intrusive granite which hosts shallow dipping quartz veining.
A successful drilling program in Q4 2016 delineated an initial MRE which was published on February 24, 2017 as part of the updated Global Mineral Resource and Reserve Statement for the Asanko Gold Mine.
Table 2: Akwasiso Mineral Resource Estimate, as at December 31, 2016
Qualified Persons Statements
Phil Bentley, Asanko Executive: Geology and Resources (Pr.Sci.Nat.) is the Asanko Qualified Person under NI 43-101 guidelines who assumes technical responsibility for Mineral Resource contents of this news release. The December 2016 MRE for Akwasiso was prepared by Charles J. Muller, B.Sc. Geology (Hons), PR.Sci.Nat., MGSSA, a Director of CJM Consulting Pty Ltd. ("CJM") of Johannesburg, South Africa. The MRE is reported in accordance with Canadian National Instrument 43-101 requirements and the South African Code of Reporting of Exploration Results (SAMREC), which is consistent with the CIM Estimation Best Practice Guidelines in Canada.