Posted in | News | Gold | Mining Business

Endeavour Mining Provides Progress Update on Houndé Gold Project

Endeavour Mining Corporation is pleased to announce that excellent progress is being made at its Houndé Gold Project in Burkina Faso, having achieved a major milestone with the Sag Mill components, which are the longest lead items, already on site and installation underway.

Construction is progressing on-time with over 85% of the total project complete and on-budget, with the first gold pour expected during the fourth quarter of 2017.

Sébastien de Montessus, President & CEO, stated: "I would like to thank the team for their continued hard work and dedication which is allowing Houndé construction to remain on-budget and on-time for a first gold pour in the fourth quarter. Most importantly, I would like to congratulate them for posting 4 million hours without a lost time injury (LTI) - continuing to build on their track record at Agbaou, which was also built without an LTI incident.

Following a two year period without drilling, we are also excited to have restarted exploration activities to focus on delineating high-grade targets, with results expected to be published in the second half of the year."  

Key milestones achieved to date include:

  • 4.0 million man-hours have been worked without a lost time injury.
  • 100% of the procurement has been complete, reducing cost over-run risk, and less than $120 million out of the forecasted $327 million total project capex remains to be spent (representing less than 35%).
  • SAG and ball mill plinths concrete has been completed, components arrived on site and are currently being installed.
  • The TSF Cell 1 (shown in the top portion of the below picture) construction is complete, TSF Cell 2 construction has commenced, and ROM pad extension is underway.
  • The power station concrete civils is complete and the 90kv overhead power line construction is 90% complete. Power from the national grid is scheduled for end of July 2017.
  • Open pit pre-strip mining at the Main Vindaloo open pit commenced in late December 2016. Mining of ore has also commenced with a mine plan to have 600,000 tonnes of stockpiled ore on the ROM pad during plant commissioning.
  • Construction of the 300-person permanent accommodation village and resettlement (pictured below) has been completed.  
  • The construction of the water harvest dam decant tower is complete, with water already being pumped to the water storage dam.
  • Over 2,000 personnel including contractors are currently employed on-site, more than 94% of which are Burkinabe.
  • Following a two year period without exploration drilling, activities resumed in early 2017 to focus on delineating high-grade targets such as Bouere and Kari Pump, Sia, and Kari Fault, in addition to preforming reconnaissance drilling.

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.