Posted in | News | Copper | Mining Business

Norsemont Mining Reports Feasibility Study Results from Constancia Copper Project

Norsemont Mining Inc. (TSX: NOM, BVL: NOM) today announced the results of the Feasibility Study optimization on the Company's 100% owned Constancia Copper Project. Ausenco Solutions Canada Inc. led and prepared the FSO and related NI 43-101Technical Report.

"The final results of the optimisation study are within the range previously announced by the Company on December 30, 2010," said Patrick Evans, CEO of Norsemont Mining. "The study delivers an economically robust, technically credible and environmentally sound development plan for the Constancia project."

The Constancia copper deposit is a large-scale porphyry deposit located in an established mining district in the highlands of Southern Peru with access to good infrastructure.  The FSO supports the development of a low-cost open pit mine with a nominal 70,000 tonnes per day (tpd) sulphide concentrator plant producing high-grade commercial concentrates of copper and molybdenum with throughput ranging up to 76,000 tpd depending on ore type.  Silver and a small quantity of gold at payable levels will report to the copper concentrate.

The Constancia FSO is based on the Constancia and San Jose zones of mineralisation ("the Constancia deposit"), which were the first discoveries within Norsemont's Peruvian mineral concessions. The main focus of the FSO was to evaluate the potential to increase mine throughput during the later years of the projected mine life to effectively achieve an average life of mine throughput of 70,000 tpd. A review of the in-pit reserves was also carried out as part of the FSO and as a result of increasing the metal prices for the pit optimization parameters to reflect the current metal price environment, the in-pit reserves were increased by approximately 34%.  With the increase in in-pit reserves, the life of mine (LOM) has also been extended by one year to a total of 16 years.

"The results of the FSO have provided for a more robust LOM throughput which equates to an increase in average annual concentrate production by approximately 28%. We are pleased with the results of the FSO.  We are also anticipating the results from the Pampacancha scoping study and our ongoing exploration program which may have the potential to further augment our global resource," Norsemont's President and COO Bob Baxter reported. "The projected average operating costs are well within the range of current peer group operating costs and highlight the robustness of the Constancia Project."

Further potential exists to increase the global Constancia resource with the successful exploration of both the Pampacancha and Chilloroya South prospects, which are in close proximity to the Constancia deposit.  During Q4 2010, Norsemont contracted SRK CONSULTING (CANADA) INC.(SRK), a British Columbia corporation, to complete a scoping study on the Pampacancha prospect which is expected to be completed by Q2 2011.  In addition to the scoping study, a new exploration program for Pampacancha and Chilloroya South discoveries has been approved by the Board of Directors.  The initial budget for the current [in-fill] exploration program is $4 million. Subsequent increases in the exploration budget will be based on the success of this program.

Annual revenue is determined by applying the relevant metal prices to the annual payable metal production estimated for each operating year. Sales prices have been applied to all LOM production without provision for escalation or hedging. Annual cash flow projections were estimated over the LOM based on the projected estimates of capital expenditures, production costs and sales revenue. The sales revenue is based on the production of copper and molybdenum. Silver and gold are also present in the copper concentrates in the form of saleable by-product credits. Constancia is subject to a sliding-scale state royalty, which is projected to be 3% over the LOM, as well as a 0.5% royalty (capped at $10M over LOM) payable to the original property owner.

The post-tax cash flow model for the FSO was based on the 2009 NI 43-101 model which was prepared by Norsemont with independent expert support from Picon and Associates, a specialist tax consultant in Lima, Peru. The values used in the FSO model do not take into account escalation and financing costs, which continue to be investigated by Norsemont.

The FSO focused on the major elements of the project, mining, plant throughput, tailings and waste management and water management systems.

Capital Costs

The total capital cost estimate (includes direct and indirect costs) to design, construct and commission the Constancia facilities is estimated to be $920 million in development capital, an increase of approximately $74 million from the 2009 development costs that supported the 2009 feasibility study (FS) . Sustaining capital over the LOM is estimated to be $240 million, which is an increase of approximately $92 million from the 2009 FS sustaining capital requirements.  Mobile mining equipment and the owner's construction equipment are included in the capital costs estimate.  It is proposed that the owner will self-construct the bulk earthworks.

The accuracy of the capital and operating cost estimates reflects the level of detail of engineering design for each element of the project. Some aspects of the projects costs were updated in the FSO whilst others aspects remain unchanged from the FS.

Operating Costs

The average LOM operating cost for the mining operation, including pre-stripping, is $1.17 per tonne mined. These costs include drilling, blasting, loading, hauling, road and dump maintenance and general mining support. Mill process operating costs average $3.85 per tonne of ore, which includes crushing and conveying, grinding and classification, flotation and regrind, concentrate thickening, filtration and dewatering, tailings disposal and mill ancillary services. General and administrative costs are $0.48 per tonne of ore.

Total cash cost is estimated at $0.93 per payable pound of copper including the mining royalty, transportation, marketing fees, treatment and refining charges, government royalty, and  by-product credits. Total cash cost including sustaining capital is $1.02 per payable pound of copper.

Mining & Production

The mining process at Constancia has not changed from the 2009 FS and is still a conventional modern hard rock open pit operation, supplying the nominal concentrator production capacity of approximately 70,000 tpd. However, throughput, metal recoveries and plant output will vary depending on the ore type being processed. Average annual production is 170 million pounds of recovered copper, 2,960 tonnes of recovered molybdenum, 1.8 million ounces of recovered silver, and approximately 10,800 ounces of gold as a by-product credit over the 16 year mine life. Over the first five years of production the Constancia mine is expected to produce 235 million pounds of recovered copper annually (107,000 tonnes of payable copper annually).

Constancia Mine Parameters

The proposed mine and all supporting infrastructure is largely the same as presented in the 2009 Technical Report.  The main changes relate to the grinding circuit equipment in order to achieve the increased throughput from a nominal 50,000 tpd to 70,000 tpd when treating hypogene ore. The changes are reflected in the replacement of a single SAG mill with a dual-train circuit including two 36 foot SAG mills and two 26 foot ball mills and deferral of the pebble crusher circuit to year 6.

Constancia Mineral Resource Report

The mineral resource for the Constancia project has not changed since the release of the 2009 Technical Report. However, computations of global tonnage and grade estimates for the FSO were revised using more appropriate pit optimization parameters which have been checked and verified by SRK.  The copper cut-off grades of 0.25% Cu, 0.20% Cu and 0.15% Cu still correspond to those applied by Norsemont in the FSO. These cut-off grades do not represent an independent assessment by AUSENCO of an economic cut-off.  The Constancia deposit includes the Constancia and San Jose zones.

Constancia Mineral Reserves Report

The Constancia Mineral Reserve is the Measured and Indicated Resource contained in the proposed open pit mine that can be processed profitably and is scheduled for treatment in the FSO LOM plan.

Since revenue is derived from four payable components (copper, molybdenum, silver plus minor payable gold), Mineral Reserve reporting is based on a Net Smelter Return (NSR) cut-off that is estimated using the metal prices and other treatment, recovery and concentrate realisation parameters. In order to better reflect the changes in metal prices since the issue of the 2009 FS, improved metal prices for the optimization parameters were used for the FSO.

Qualified Person and Data Verification

The Feasibility Study Optimization and NI 43-101 Technical Report were prepared by an integrated engineering team led by Ausenco as the primary author of the Technical Report.  The following Qualified Persons were involved in the development of the FSO and the Technical Report, and have reviewed and approved the contents of this news release:

  • Plant design and cost estimate preparation for the FSO was managed Greg Lane, MAusIMM, General Manager of Technical Solutions, Ausenco Minerals & Metals.
  • Mining studies were completed and Mineral Reserves reported by Dino Pilotto of SRK Consulting, a Registered Professional Engineer, P.Eng. in Saskatoon and Alberta.
  • Engineering design and costing of the tailings management facility, waste dump and surface water management infrastructure were the responsibility of Thomas Kerr, President of Knight Piesold and Co. (USA), a Registered Professional Engineer, P.Eng in British Columbia, Ontario and P.E. in California, Colorado and Alaska.
  • Pit geotechnical design parameters were provided by Robert Cummings, Registered Professional Engineer in Arizona.
Source:

Norsemont Mining Inc.

Citations

Please use one of the following formats to cite this article in your essay, paper or report:

  • APA

    Norsemont Mining Inc.. (2019, February 18). Norsemont Mining Reports Feasibility Study Results from Constancia Copper Project. AZoMining. Retrieved on November 23, 2024 from https://www.azomining.com/News.aspx?newsID=2843.

  • MLA

    Norsemont Mining Inc.. "Norsemont Mining Reports Feasibility Study Results from Constancia Copper Project". AZoMining. 23 November 2024. <https://www.azomining.com/News.aspx?newsID=2843>.

  • Chicago

    Norsemont Mining Inc.. "Norsemont Mining Reports Feasibility Study Results from Constancia Copper Project". AZoMining. https://www.azomining.com/News.aspx?newsID=2843. (accessed November 23, 2024).

  • Harvard

    Norsemont Mining Inc.. 2019. Norsemont Mining Reports Feasibility Study Results from Constancia Copper Project. AZoMining, viewed 23 November 2024, https://www.azomining.com/News.aspx?newsID=2843.

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.