Tethys Petroleum Provides Update on Operations in Kazakhstan

Tethys Petroleum Limited today gave an update on its operations in Kazakhstan.

AKD08 ("Doto")

The AKD08 ("Doto") exploration well has reached a total depth of 3,556 metres and electric logs have been run to TD in the 8 1/2" hole section. As was previously announced, hydrocarbon indications have been observed in both the Cretaceous and Jurassic sections whilst drilling and from the wireline logs. The well has now been cemented off at the lower Triassic level and the well is being prepared for a testing program on both the Jurassic and on the Cretaceous intervals. Testing of the first zone is expected to take place by the end of December once appropriate Kazakh regulatory approvals have been received. The deeper Triassic section will not be tested as only low permeability zones were encountered.

AKD09 ("Dexa")

The AKD09 ("Dexa") exploration well has reached a total depth of 2,452 metres and electric logs have been run. The primary exploration target of the well, the Cretaceous "Doris" channel sandstone, does not appear to be hydrocarbon bearing at this location. The well was targeted at this level to evaluate the potential upside of the Doris field in the area to the north-east of the field. The well is now being prepared to drill a semi-horizontal Doris development well in the Jurassic Limestone sequence close to the Doris field discovery AKD01 well which tested 1,373 barrels of 46° API oil per day from this sequence. The AKD01 well has not to date been commercially produced from the Jurassic as it is currently producing from the Cretaceous sand and therefore this area of the reservoir will be unswept. The AKD09H well will provide a longer production interval in this fractured reservoir sequence using an approach which is commonly used in such zones.

KBD01 ("Kalypso")

A successful cementing procedure has been carried out on the KBD01 well and a comprehensive stimulation and subsequent testing programme, to be conducted primarily by Schlumberger, will commence mid-December, initially on the Permo-Carboniferous interval. The testing programme will involve acid-fracture stimulation of the carbonate interval approximately 4,100 metres below the surface and will take up to one month to complete. Electric logs run over this section and drilling data indicated more than 100 metres of gross potential hydrocarbon bearing zones.

Further Exploration

The initial results of the additional seismic acquired in the summer of 2013 are very promising and the first interpretation indicates a prospect in the Kul-Bas Exploration and Production Contract area to the west of the Akkulka Exploration Contract Area (to be named "Klymene"), with the potential to be an order of magnitude bigger than the Doris oil discovery and surrounding prospects (the geographical area of the prospect is up to ten times the areal extent of the Doris oil field). It appears to have good four-way structural closure and positive indications on the newly interpreted seismic. Prospective Resources to NI 51-101 standards are being independently prepared with further information expected to be provided early next year. It is expected to spud this new well in the first half of 2014.

Shallow Gas Drilling program

Currently the tied in gas wells on Kyzyloi and Akkulka can produce approximately 360 thousand cubic metres per day (Mcm/d) (13 million cubic feet per day (MMcf/d)). At the current gas price (recently doubled in price to net USD 65 per Mcm (USD 1.84)) this production generates approximately USD 8.3 million per annum in revenue.

The forward gas programme has two aspects: those wells that have been previously drilled and tested that will be tied in and new shallow gas wells with up to 10 new wells planned for 2014.

Previously drilled and tested wells will be brought on stream over the next 12 months, at different stages dependent on their particular location and contract status.

The AKK14 well was drilled in 2008 and tested at 195 Mcm/d (6.9 MMcf/d) in the Tasaran horizon. This gas well has been approved and incorporated under the Akkulka Production Contract. It will be worked over and brought on production in January 2014 and is already tied into the pipeline system.

The AKK05 well was drilled in 2005 and tested at 223Mcm/d (7.9 MMcf/d). This will be worked over in February 2014 whereupon it can be produced for 90 days test production. It is expected that it will be approved and incorporated under the Kyzyloi Production Contract by 3Q 2014 whereupon it can be placed on permanent production, also already being tied into the infrastructure.

The AKK15 and AKK16 wells were drilled in 2008 and tested at 195 Mcm/d (6.9 MMcf/d) and 289 Mcm/d (10.2 MMcf/d) respectively. Additional wells will be drilled in proximity to AKK15 and AKK16 next year and these pipelines will be laid and tied into the optimised infrastructure.

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.