Lithium Americas Provides Update on Cauchari-Olaroz Project in Argentina

Lithium Americas Corp. (TSX:LAC)(OTCQX:LACDF) ("Lithium Americas" or the "Company") is pleased to provide an update for the Cauchari-Olaroz lithium project ("Cauchari-Olaroz") in Jujuy province, Argentina.

Minera Exar S.A. ("Minera Exar"), a 50/50 joint venture company ("JV") between Lithium Americas and Sociedad Quimica y Minera de Chile S.A. ("SQM"), continues to advance the Cauchari-Olaroz project as planned. As previously announced, Minera Exar is pursuing a development plan at Cauchari-Olaroz that targets 50,000 tonnes per annum ("tpa") of lithium carbonate production capacity in two stages, with each stage consisting of 25,000 tpa of lithium carbonate. A feasibility study ("Stage 1 DFS") on the first stage of 25,000 tpa of lithium carbonate production capacity ("Stage 1") is nearing completion.

The qualified persons ("QPs") responsible for preparing the Stage 1 DFS have completed substantially all capital cost development analysis for Stage 1, with remaining work related primarily to confirming SQM's operating cost estimates to a NI 43-101 compliant feasibility study standard. The Company and the QPs can confirm at this time the following:

  • The project capital cost estimate for the construction of Stage 1 is expected to be US$420 - US$430 million before value-added and other applicable taxes ("Taxes") and working capital;
     
  • The operating cost estimate will be at the low end of the cost curve compared to producing lithium operations;
     
  • The parties expect to be in a position to commence construction in the first half of 2017;
     
  • The current construction schedule is estimated at two years with production forecast to start in 2019; and
     
  • During the construction period, Minera Exar's direct employment in the province of Jujuy is estimated to be at least 800 people; once in operation, Minera Exar is expected to employ approximately 300 people in permanent positions.

Lithium Americas will be responsible for contributing 50% of capital expenditures for the construction of Stage 1, amounting to approximately US$210 - US$215 million before Taxes and working capital.

Technical Information

Ernie Burga, a qualified person under NI 43-101, has reviewed and approved the scientific and technical information in this press release. Further information about the scientific and technical information on Cauchari-Olaroz in this press release, including a summary of data verification measures, and a description of the assumptions, parameters and risks associated with this information, will be available in a NI 43-101 Technical Report that will be filed by Lithium Americas in connection with its disclosure of the results of the Stage 1 DFS.

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.